Bronx Park Tree Planting FY22

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    25% complete

This project will plant new and replacement park trees in the Bronx.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2021
Projected Completion Date: January 2022
Completion Date: March 2023

Procurement

Start Date: March 2023
Projected Completion Date: October 2022
Completion Date: March 2024

Construction

Start Date: March 2024
Projected Completion Date: September 2025

Understand how we build parks.

Funding

Total Funding: $4,882,000
Funding Sources:
  • City Council
  • Mayoral
  • Private

Location

Various locations in The Bronx

Project Staff

Contact NYC Parks about this project

Last updated: 01/17/2025