Brooklyn Street Tree Planting FY22 - Community Boards 1, 4

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new and replacement trees in Community Boards 1 and 4 in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2021
Projected Completion Date: January 2022
Completion Date: November 2021

Procurement

Start Date: November 2021
Projected Completion Date: August 2022
Completion Date: April 2023

Construction

Start Date: April 2023
Projected Completion Date: April 2024
Completion Date: June 2023

Understand how we build parks.

Funding

Total Funding: $500,000
Funding Sources:
  • City Council
  • Private

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024