Brooklyn Street Tree Planting FY22 - Community Boards 2-3
-
100% complete
-
100% complete
-
100% complete
This project will plant new and replacement trees in Community Boards 2 and 3 in Brooklyn.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2021
Projected Completion Date:
January 2022
Completion Date:
November 2021
Procurement
Start Date: November 2021
Projected Completion Date:
August 2022
Completion
Date:
April 2023
Construction
Start Date: August 2023
Projected Completion Date:
August 2024
Completion Date: February 2024
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Private
Last updated: 11/22/2024