Brooklyn Street Tree Planting FY22 - Community Boards 6, 7, 10

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new and replacement trees in Community Boards 6, 7, and 10 in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2021
Projected Completion Date: January 2022
Completion Date: December 2021

Procurement

Start Date: December 2021
Projected Completion Date: September 2022
Completion Date: May 2023

Construction

Start Date: August 2023
Projected Completion Date: August 2024
Completion Date: August 2024

Understand how we build parks.

Funding

Total Funding: $2,990,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project