Brooklyn Street Tree Planting FY22 - Community Boards 6, 7, 10
-
100% complete
-
100% complete
-
100% complete
This project will plant new and replacement trees in Community Boards 6, 7, and 10 in Brooklyn.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2021
Projected Completion Date:
January 2022
Completion Date:
December 2021
Procurement
Start Date: December 2021
Projected Completion Date:
September 2022
Completion
Date:
May 2023
Construction
Start Date: August 2023
Projected Completion Date:
August 2024
Completion Date: August 2024
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Private
Last updated: 11/22/2024