Manhattan Lower East Side Street Tree Planting and Community Greening FY22

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new and replacement trees on the Lower East Side of Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2021
Projected Completion Date: January 2022
Completion Date: November 2021

Procurement

Start Date: November 2021
Projected Completion Date: August 2022
Completion Date: June 2023

Construction

Start Date: August 2023
Projected Completion Date: August 2024
Completion Date: February 2024

Understand how we build parks.

Funding

Total Funding: $300,000
Funding Source: Mayoral

Location

Various locations in Manhattan

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024