Brooklyn Park Tree Planting FY22

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    32% complete

This project will plant new and replacement park trees in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2021
Projected Completion Date: January 2022
Completion Date: January 2022

Procurement

Start Date: January 2022
Projected Completion Date: October 2022
Completion Date: May 2023

Construction

Start Date: January 2024
Projected Completion Date: June 2025

Understand how we build parks.

Funding

Total Funding: $2,444,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024