Manhattan Park Tree Planting FY22

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    94% complete

This project will plant new and replacement park trees in Manhattan.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2021
Projected Completion Date: January 2022
Completion Date: January 2022

Procurement

Start Date: January 2022
Projected Completion Date: October 2022
Completion Date: June 2023

Construction

Start Date: August 2023
Projected Completion Date: January 2025

Understand how we build parks.

Funding

Total Funding: $993,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024