PS 192 Playground Reconstruction Phase 2

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install additional new play equipment, safety surface and fencing at PS 192 in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2014
Projected Completion Date: February 2015
Completion Date: February 2015

Procurement

Start Date: April 2015
Projected Completion Date: September 2015
Completion Date: April 2015

Construction

Start Date: July 2015
Projected Completion Date: September 2015
Completion Date: September 2015