PS 192 Playground Reconstruction Phase 2
-
100% complete
-
100% complete
-
100% complete
This project will install additional new play equipment, safety surface and fencing at PS 192 in Brooklyn.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2014
Projected Completion Date:
February 2015
Completion Date:
February 2015
Procurement
Start Date: April 2015
Projected Completion Date:
September 2015
Completion
Date:
April 2015
Construction
Start Date: July 2015
Projected Completion Date:
September 2015
Completion Date: September 2015
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 11/22/2024