Riverside Park Dinosaur Playground Reconstruction
-
30% complete
-
0% complete
-
0% complete
This project will reconstruct the Dinosaur Playground in Riverside Park. Improvements to address severe drainage issue, ADA access, play equipment, safety surface, spray shower, seating, landscaping and fencing.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2023
Projected Completion Date:
November 2024
Adjusted Completion Date:
April 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Riverside Park, Manhattan
Riverside Drive at West 97th Street
Community Board: 07, 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024