Haffen Park Pool Complex Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the pool complex at Haffen Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2021
Projected Completion Date:
October 2022
Completion Date:
February 2023
Procurement
Start Date: February 2023
Projected Completion Date:
November 2023
Adjusted Completion
Date:
March 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Haffen Park, Bronx
1814 Burke Avenue
Community Board: 12
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project