Van Cortlandt House Museum Fence Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    28% complete

This project will reconstruct the wrought iron fence at Van Cortland House Museum.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2022
Projected Completion Date: February 2023
Completion Date: March 2023

Procurement

Start Date: March 2023
Projected Completion Date: March 2024
Completion Date: June 2024

Construction

Start Date: September 2024
Projected Completion Date: September 2025

Understand how we build parks.

Funding

Total Funding: $2,700,000
Funding Source: City Council

Location

Van Cortlandt Park, Bronx
6036 Broadway, between West 242nd Street and West 246th Street
Community Board: 07, 08, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024