Schmul Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    2% complete

This project will reconstruct a portion of the playground in Schmul Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2021
Projected Completion Date: September 2022
Completion Date: March 2023

Procurement

Start Date: March 2023
Projected Completion Date: March 2024
Completion Date: June 2024

Construction

Start Date: October 2024
Projected Completion Date: January 2026

Understand how we build parks.

Funding

Total Funding: $2,789,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Schmul Park, Staten Island
Wild Avenue, Melvin Avenue, and Pearson Street
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024