Schmul Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    4% complete

This project will reconstruct a portion of the playground in Schmul Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2021
Projected Completion Date: September 2022
Completion Date: March 2023

Procurement

Start Date: March 2023
Projected Completion Date: March 2024
Completion Date: June 2024

Construction

Start Date: October 2024
Projected Completion Date: January 2026

Understand how we build parks.

Funding

Total Funding: $2,789,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Schmul Park, Staten Island
Wild Avenue, Melvin Avenue, and Pearson Street
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 01/17/2025