Riverside Park 78th Street Ramp Reconstruction
-
100% complete
-
85% complete
-
0% complete
This project will reconstruct the ramp near 78th Street in Riverside Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2022
Projected Completion Date:
March 2023
Completion Date:
March 2023
Procurement
Start Date: March 2023
Projected Completion Date:
March 2024
Adjusted Completion
Date:
December 2024
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Riverside Park, Manhattan
Riverside Drive and West 78th Street
Community Board: 07, 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024