Brooklyn, Queens, and Staten Island Sidewalk Reconstruction FY12
-
100% complete
-
100% complete
-
100% complete
This multisite contract will reconstruct damaged sidewalks in Brooklyn, Queens and Staten Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2011
Projected Completion Date:
February 2012
Completion Date:
January 2012
Procurement
Start Date: January 2012
Projected Completion Date:
October 2012
Completion
Date:
March 2013
Construction
Start Date: April 2013
Projected Completion Date:
April 2014
Completion Date: October 2013