Taaffe Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will install new pavement, fencing and play equipment at Taaffe Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2014
Projected Completion Date:
February 2015
Completion Date:
February 2015
Procurement
Start Date: July 2015
Projected Completion Date:
December 2015
Completion
Date:
July 2015
Construction
Start Date: April 2016
Projected Completion Date:
September 2016
Completion Date: September 2016
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Taaffe Playground, Brooklyn
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks