Daniel Boone Playground Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct Daniel Boone Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: June 2023

Procurement

Start Date: June 2023
Projected Completion Date: September 2025
Adjusted Completion Date: July 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Borough President
  • City Council

Location

Daniel Boone Playground, Bronx
West Farms Road and Boone Avenue
Community Board: 03

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024