Daniel Boone Playground Reconstruction
-
100% complete
-
40% complete
-
0% complete
This project will reconstruct Daniel Boone Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2022
Projected Completion Date:
April 2023
Completion Date:
June 2023
Procurement
Start Date: June 2023
Projected Completion Date:
September 2025
Adjusted Completion
Date:
July 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Daniel Boone Playground, Bronx
West Farms Road and Boone Avenue
Community Board: 03
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024