Eastchester Playground Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct the playground and handball courts in Eastchester Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2021
Projected Completion Date: December 2022
Completion Date: April 2023

Procurement

Start Date: April 2023
Projected Completion Date: April 2024
Adjusted Completion Date: February 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Eastchester Playground, Bronx
Adee Avenue and Tenbroeck Ave
Community Board: 11

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024