Bronx Park East Botanical Garden Pedestrian Access Ramp Construction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will construct an accessible pedestrian ramp to the New York Botanical Garden in Bronx Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2022
Projected Completion Date: June 2023
Completion Date: July 2023

Procurement

Start Date: July 2023
Projected Completion Date: July 2024
Adjusted Completion Date: March 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: City Council

Location

Bronx Park, Bronx
Bronx Park East and Waring Avenue
Community Board: 06, 07, 11, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024