Surf Playground Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play area, including pavement, fencing, safety surfacing and play equipment, at Surf Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2014
Projected Completion Date: September 2014
Completion Date: February 2015

Procurement

Start Date: July 2015
Projected Completion Date: December 2015
Completion Date: July 2015

Construction

Start Date: September 2015
Projected Completion Date: May 2016
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $480,000
Funding Source: Mayoral

Location

Surf Playground, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025