  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the water service to Isham Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2012
Projected Completion Date: July 2012
Completion Date: May 2013

Procurement

Start Date: May 2013
Projected Completion Date: January 2014
Completion Date: February 2014

Construction

Start Date: April 2014
Projected Completion Date: April 2015
Completion Date: April 2015

Understand how we build parks.

Funding

Total Funding: $692,000
Funding Source: City Council

Location

Isham Park, Manhattan
Isham Street between Broadway and Seaman Avenue
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project