Hickman Playground Reconstruction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Hickman Playground.

Project Notes

Project Update: Design is complete and permitting and legal review of the contract are in progress.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2023
Projected Completion Date: May 2025
Completion Date: December 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • City Council
  • Mayoral

Location

Hickman Playground, Brooklyn
Veterans Avenue between East 66th Street and East 68th Street
Community Board: 18

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025