Thomas Greene Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install new play equipment and fencing at Thomas Greene Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2013
Projected Completion Date: March 2014
Completion Date: March 2014

Procurement

Start Date: June 2015
Projected Completion Date: November 2015
Completion Date: October 2014

Construction

Start Date: April 2015
Projected Completion Date: June 2015
Completion Date: June 2015

Understand how we build parks.

Funding

Total Funding: $150,000
Funding Sources:
  • Mayoral
  • City Council

Location

Thomas Greene Playground, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025