Paerdegat Park Ballfields Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct the ballfields at Paerdegat Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2021
Projected Completion Date:
December 2022
Completion Date:
February 2023
Procurement
Start Date: February 2023
Projected Completion Date:
February 2024
Adjusted Completion
Date:
April 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Paerdegat Park, Brooklyn
Farragut Road between East 40th Street and East 41st Street
Community Board: 17
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024