PO Jeff Herman Ballfield Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will convert the existing asphalt field to a synthetic turf field and reconstruct the handball court and basketball courts at Police Officer Jeff Herman Ballfield in McDonald Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2021
Projected Completion Date: December 2022
Completion Date: June 2023

Procurement

Start Date: June 2023
Projected Completion Date: June 2024
Adjusted Completion Date: March 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: City Council

Location

McDonald Playground, Brooklyn
McDonald Avenue between Avenues S & T
Community Board: 15

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024