McKinley Park Playground Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct the playground at McKinley Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2022
Projected Completion Date:
August 2023
Completion Date:
August 2023
Procurement
Start Date: August 2023
Projected Completion Date:
August 2024
Adjusted Completion
Date:
April 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
McKinley Park, Brooklyn
Bay Ridge Parkway between 7th Avenue and Fort Hamilton Parkway
Community Board: 10
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024