Gwen Ifill Park Construction
-
50% complete
-
0% complete
-
0% complete
This project will construct a playground, basketball courts, adult fitness equipment, entry plazas, and pathways at Gwen Ifill Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2021
Projected Completion Date:
September 2023
Adjusted Completion Date:
December 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Gwen Ifill Park, Queens
129th Avenue between 172nd Street and 176th Street
Community Board: 12
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024