Woodtree Playground Basketball Courts Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the basketball courts at Woodtree Playground.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2021
Projected Completion Date:
December 2022
Completion Date:
March 2023
Procurement
Start Date: March 2023
Projected Completion Date:
March 2024
Completion
Date:
January 2025
Construction
Start Date: March 2025
Projected Completion Date:
March 2026
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Woodtree Playground, Queens
20th Avenue between 37th Street and 38th Street
Community Board: 01
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 02/21/2025