Cross Island Parkway Waters Edge Drive Playground Construction
-
100% complete
-
0% complete
-
0% complete
This project will construct a playground next to the Cross Island Parkway near Waters Edge Drive.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2021
Projected Completion Date:
April 2023
Completion Date:
August 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Cross Island Parkway, Queens
24th Avenue and Waters Edge Drive
Community Board: 07, 11, 13
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024