Park of the Americas Basketball Court Reconstruction
-
100% complete
-
85% complete
-
0% complete
This project will reconstruct the basketball court and adjacent entrance at Park of the Americas.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2022
Projected Completion Date:
July 2023
Completion Date:
August 2023
Procurement
Start Date: August 2023
Projected Completion Date:
August 2024
Adjusted Completion
Date:
January 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Park Of The Americas, Queens
104th Street and 42nd Avenue
Community Board: 04
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024