Kissena Corridor Park Lighting Construction
-
100% complete
-
100% complete
-
0% complete
This project will construct lighting and a pathway at Kissena Corridor Park.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2022
Projected Completion Date:
June 2023
Completion Date:
June 2023
Procurement
Start Date: June 2023
Projected Completion Date:
June 2024
Completion
Date:
February 2025
Construction
Start Date: February 2025
Projected Completion Date:
February 2026
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Kissena Corridor Park, Queens
146th Street, 56th Road and Colden Street
Community Board: 07
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 02/21/2025