Marine Park Bike Path Restoration

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will restore damaged portions of the Plumb Beach bike path in Marine Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2013
Projected Completion Date: May 2014
Completion Date: May 2014

Procurement

Start Date: June 2015
Projected Completion Date: November 2015
Completion Date: September 2014

Construction

Start Date: October 2014
Projected Completion Date: November 2014
Completion Date: December 2014

Understand how we build parks.

Funding

Total Funding: $275,000
Funding Source: City Council

Location

Marine Park, Brooklyn

 

Project Staff

Project Liaison: Davey Ives