Marine Park Bike Path Restoration
-
100% complete
-
100% complete
-
100% complete
This project will restore damaged portions of the Plumb Beach bike path in Marine Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2013
Projected Completion Date:
May 2014
Completion Date:
May 2014
Procurement
Start Date: June 2015
Projected Completion Date:
November 2015
Completion
Date:
September 2014
Construction
Start Date: October 2014
Projected Completion Date:
November 2014
Completion Date: December 2014
Understand how we build parks.
Funding
Funding Source: City Council
Location
Marine Park, Brooklyn
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024