Conference House Pavilion Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Conference House Pavilion in Conference House Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2013
Projected Completion Date: March 2015
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: April 2017
Completion Date: November 2017

Construction

Start Date: January 2018
Projected Completion Date: January 2019
Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $6,091,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Conference House Park, Staten Island
Hylan Boulevard and Satterlee Street at Arthur Kill
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024