College Point Fields Soccer Field Construction
-
100% complete
-
0% complete
-
0% complete
This project will reconstruct the existing baseball field #3 as mini soccer field at College Point Fields.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2022
Projected Completion Date:
January 2024
Completion Date:
June 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
College Point Fields, Queens
Linden Place, 23rd Avenue, and 130th Street
Community Board: 07
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024