Hoffman Park Reconstruction
-
100% complete
-
0% complete
-
0% complete
This project will reconstruct Hoffman Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2022
Projected Completion Date:
September 2023
Completion Date:
June 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
Location
Hoffman Park, Queens
Hoffman Drive between 58th Avenue and Woodhaven Boulevard
Community Board: 04
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024