Ruoff Triangle Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will install new concrete pavement, concrete curbs and trees at Ruoff Triangle.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2015
Projected Completion Date:
August 2015
Completion Date:
August 2015
Procurement
Start Date: April 2016
Projected Completion Date:
September 2016
Completion
Date:
September 2016
Construction
Start Date: March 2017
Projected Completion Date:
July 2017
Completion Date: September 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Ruoff Triangle, Queens
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024