Ruoff Triangle Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install new concrete pavement, concrete curbs and trees at Ruoff Triangle.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2015
Projected Completion Date: August 2015
Completion Date: August 2015

Procurement

Start Date: April 2016
Projected Completion Date: September 2016
Completion Date: September 2016

Construction

Start Date: March 2017
Projected Completion Date: July 2017
Completion Date: September 2017

Understand how we build parks.

Funding

Total Funding: $102,000
Funding Source: Mayoral

Location

Ruoff Triangle, Queens

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024