Grand Slope Staircase Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    65% complete

This project will reconstruct the staircase at Grand Slope.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2021
Projected Completion Date: November 2022
Completion Date: November 2022

Procurement

Start Date: November 2022
Projected Completion Date: August 2023
Completion Date: August 2024

Construction

Start Date: September 2024
Projected Completion Date: September 2025

Understand how we build parks.

Funding

Total Funding: $300,000
Funding Source: City Council

Location

Grand Slope, Queens
Grand Avenue and Kneeland Avenue at Haspel Street
Community Board: 04

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024