American Triangle Reconstruction
-
100% complete
-
85% complete
-
0% complete
This project will reconstruct American Triangle.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2022
Projected Completion Date:
April 2023
Completion Date:
May 2023
Procurement
Start Date: May 2023
Projected Completion Date:
April 2024
Adjusted Completion
Date:
January 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
American Triangle, Queens
102nd Street, 41st Avenue, National Street
Community Board: 04
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024