American Triangle Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct American Triangle.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: May 2023

Procurement

Start Date: May 2023
Projected Completion Date: April 2024
Completion Date: January 2025

Construction

Start Date: March 2025
Projected Completion Date: March 2026

Understand how we build parks.

Funding

Total Funding: $750,000
Funding Source: City Council

Location

American Triangle, Queens
102nd Street, 41st Avenue, National Street
Community Board: 04

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 02/21/2025