Fort Washington Park Discovery Playground Public Restroom Building Construction
-
100% complete
-
5% complete
-
0% complete
This project will construct a public restroom building at Discovery Playground in Fort Washington Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2022
Projected Completion Date:
April 2023
Completion Date:
March 2024
Procurement
Start Date: March 2024
Projected Completion Date:
March 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Fort Washington Park, Manhattan
Hudson River near West 163rd Street
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024