Riverside Park South West 69th Street Transfer Bridge Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will stabilize and restore existing structures with historically appropriate materials at Riverside Park South. This project will also include adding lighting on gantry towers, providing interpretive signage at ground level and removing 65 additional piles at Pier F.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2015
Projected Completion Date: December 2016
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: February 2020
Completion Date: October 2024

Construction

Start Date: January 2025
Projected Completion Date: April 2026

Understand how we build parks.

Funding

Total Funding: $6,596,000
Funding Sources:
  • Federal
  • Mayoral
  • Private

Location

Riverside Park South, Manhattan
Hudson River at West 69th Street
Community Board: 07

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024