Riverside Park South West 69th Street Transfer Bridge Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will stabilize and restore existing structures with historically appropriate materials at Riverside Park South. This project will also include adding lighting on gantry towers, providing interpretive signage at ground level and removing 65 additional piles at Pier F.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2015
Projected Completion Date:
December 2016
Completion Date:
May 2019
Procurement
Start Date: May 2019
Projected Completion Date:
February 2020
Completion
Date:
October 2024
Construction
Start Date: January 2025
Projected Completion Date:
April 2026
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
- Private
Location
Riverside Park South, Manhattan
Hudson River at West 69th Street
Community Board: 07
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024