Van Cortlandt Park Green Infrastructure Construction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will install multiple green infrastructure elements throughout Van Cortlandt Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2022
Projected Completion Date: May 2023
Adjusted Completion Date: December 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Van Cortlandt Park, Bronx
Broadway, Jerome Avenue, City Line, Van Cortlandt Park South, Van Cortlandt Park East
Community Board: 07, 08, 12

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024