Manhattan East Side Coastal Resiliency Sidewalk Bioswales Construction
-
100% complete
-
100% complete
-
0% complete
This project will construct sidewalk bioswales and green infrastructure to capture storm water in Community Boards 3 and 6 in Manhattan.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2021
Projected Completion Date:
September 2022
Completion Date:
June 2022
Procurement
Start Date: June 2022
Projected Completion Date:
March 2023
Completion
Date:
July 2024
Construction
Start Date: August 2024
Projected Completion Date:
August 2027