Manhattan East Side Coastal Resiliency Sidewalk Bioswales Construction
-
100% complete
-
100% complete
-
0% complete
This project will construct sidewalk bioswales and green infrastructure to capture storm water in Community Boards 3 and 6 in Manhattan.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2021
Projected Completion Date:
September 2022
Completion Date:
June 2022
Procurement
Start Date: June 2022
Projected Completion Date:
March 2023
Completion
Date:
July 2024
Construction
Start Date: August 2024
Projected Completion Date:
August 2027
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 01/17/2025