Manhattan East Side Coastal Resiliency Sidewalk Bioswales Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct sidewalk bioswales and green infrastructure to capture storm water in Community Boards 3 and 6 in Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2021
Projected Completion Date: September 2022
Completion Date: June 2022

Procurement

Start Date: June 2022
Projected Completion Date: March 2023
Completion Date: July 2024

Construction

Start Date: August 2024
Projected Completion Date: August 2027

Understand how we build parks.

Funding

Total Funding: $5,000,000
Funding Source: Mayoral

Location

Various locations in Manhattan

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024