Van Cortlandt Park Greenhouse Stabilization
-
100% complete
-
100% complete
-
100% complete
This project will temporarily stabilize the head house at the Van Cortlandt Park Greenhouse to support mechanical systems and continued operations.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2020
Projected Completion Date:
September 2021
Completion Date:
December 2021
Procurement
Start Date: December 2021
Projected Completion Date:
September 2022
Completion
Date:
May 2022
Construction
Start Date: May 2022
Projected Completion Date:
August 2022
Completion Date: June 2022
Understand how we build parks.
Funding
Location
Van Cortlandt Park, Bronx
Van Cortlandt Park East and East 242nd Street
Community Board: 07, 08, 12
Project Staff
Project Liaison: Katerine Borrome