Bronx Green Infrastructure Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct green infrastructure to capture storm water at Magenta Playground and Watson Gleason Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2021
Projected Completion Date:
December 2021
Completion Date:
August 2021
Procurement
Start Date: August 2021
Projected Completion Date:
May 2022
Completion
Date:
June 2023
Construction
Start Date: November 2023
Projected Completion Date:
November 2024
Completion Date: August 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Magenta Playground, Bronx
Olinville Avenue & Rose Rosewood Street
Community Board: 12 -
Watson Gleason Playground, Bronx
Watson & Rosedale Avenues
Community Board: 09
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024