Bronx Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct green infrastructure to capture storm water at Magenta Playground and Watson Gleason Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2021
Projected Completion Date: December 2021
Completion Date: August 2021

Procurement

Start Date: August 2021
Projected Completion Date: May 2022
Completion Date: June 2023

Construction

Start Date: November 2023
Projected Completion Date: November 2024
Completion Date: August 2024

Understand how we build parks.

Funding

Total Funding: $889,000
Funding Source: Mayoral

Locations

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024