Brooklyn Tree-Damaged Sidewalk Reconstruction FY21 - Community Boards 7, 10-13, 15, 18
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct sidewalks damaged by adjacent city-owned trees in Community Boards 7, 10-13, 15, and 18 in Brooklyn.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2021
Projected Completion Date:
September 2021
Completion Date:
April 2021
Procurement
Start Date: April 2021
Projected Completion Date:
January 2022
Completion
Date:
January 2022
Construction
Start Date: September 2021
Projected Completion Date:
August 2022
Completion Date: August 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 11/22/2024